Kmart Distribution Centre

Ruakura Superhub, Hamilton

Client:
Calder Stewart Construction
Location:
Ruakura Superhub, Hamilton
Duration:
11 months
Completion Date:
Aug 4, 2023

Kmart Distribution Centre

Located at the Ruakura Superhub on Aka Matua Lane, the Kmart Distribution Centre comprises of a large 40,000m2 warehouse space, a main office, receiving office, dispatch office, gatehouse and bike shed. The project was designed and constructed to achieve a 4 Star Green Star As Built rating under the Green Star Design & As Built NZ v1.0. 



The site has one main electrical switch-room
located in a dedicated room with the two main switchboards, MSB-1 & MSB-2. These two MSB’s are fed off two 1500kVA transformers which are housed in individual rooms next to the main switchboard room. The 1500kVA transformers allow the site to have approximately 6000 amps for the site power.

Elektron installed:


2 x 3,000A rated MSB's, each fed off a dedicated transformer


28 x sub-distribution boards

3 x UPS's installed for 3 x dedicated comms rooms



1,250+ light fittings

Dynalite lighting control system

Energy Monitoring System



10,000m+ ducting installed for underground services

4,500m+ cable tray

135,000m+ cable

50+ light poles

Technical earthing system/dedicated bonds for comms cabinets back to a central point

From the two MSB’s the power is distributed around the site to local distribution boards. There are 28 distribution boards on this site which service the lighting and power circuits throughout the warehouse, main office, receiving office, dispatch office, gatehouse and bike shed. 

All distribution boards are manufactured from NHP modular metalwork with Schneider distribution componentry. 



ON Switchgear  manufactured all the boards for this job.


Lighting Control 


Kmart Distribution Centre has a Philips Dynalite lighting control system installed throughout the entire complex of the building from all the offices right through to the warehouse. 
The Philips Dynalite lighting control platform offers the best of breed lighting control with over 35 years of reliable service in over 35,000 projects around the world. 
Kmart Distribution Centre is provided with state-of-the-art emergency lighting, the Dali monitored lighting system, which is linked to the Dynalite. The Dynalite system does the testing and reporting on the emergency lighting system.


Energy Monitoring System 


The power monitoring system complies with the requirements of Green Star Design & As Built NZ v1.0. 
The web-based reports application allows you to select, configure, generate and manage comprehensive reports based on historical data contained within your databases. 
The reports are designed for energy/water consumption and usage, power quality compliance and analysis, and generic system usage. The reports can be generated on a defined schedule and when system events or device alarms occur. They are then distributed via email, or sent to a file share or printer.

Porro eos

Modi ad non placeat

Aut et deleniti quas. Ab consequatur cumque quaerat et ea occaecati

Projects

Similar Projects

Dec 16, 2020
5 min read

Rotokauri Transport Hub

Rotokauri Transport Hub is a local transport station in north Te Rapa, Hamilton.
Feb 13, 2023
5 min read

Tyreline

The Tyreline building consists of a 9,000m² warehouse.

Your project awaits